1320–22 N. Smedley Street
Three-story, four-unit apartment building
An attached, three-story building with four apartments in Cecil B. Moore, North Philadelphia, designed by KJO Architecture. This page shows the building’s progress and permit-level facts as work moves through its 14 milestones, from permits to move-in.
- STORIES
- 3 Stories
- DWELLING UNITS
- 4 Units
- TOTAL BUILDING AREA
- 6,397 sq ft
- ZONING
- RSA-5
About the building
What’s being built at 1320–22 N. Smedley
An attached, three-story building with four apartments, designed by KJO Architecture. It fills most of the lot, with a garage at the front and a rear yard behind.
- Full cellarA below-ground level under the building
- BalconiesOn the second and third floors
- Roof decksReached by a pilothouse, with a 42-inch parapet
- Indoor parking2 spaces off Smedley St, one van-accessible
- Fully sprinkleredFire protection to the NFPA 13 standard
- Rooftop solarSolar collectors proposed on the roof
- Rear yardEnclosed by a 6-ft privacy fence
- Recessed entryA set-back ground-floor entrance
- Address
- 1320–22 N. Smedley St, Philadelphia
- Neighborhood
- Cecil B. Moore, North Philadelphia
- Architect
- KJO Architecture
- Contractor
- Alex
- New construction
- 6,397 sq ft
- Zoning
- RSA-5
- Ground disturbed
- 2,673 sq ft
- Permit-listed cost
- $575,000
Build sequence · interactive
Watch the building go up
A step-by-step 3D simulation of how the building comes together, synced to the project’s 14 milestones. Press play or drag the timeline to see what’s happening on site and what comes next.
2 of 14 milestones complete · Est. completion Apr 26, 2027
3D model · drag to orbit
Excavation · in progress
Planned: 3 stories + roof deck
Foundations · next, from Oct 2
- Excavation
- Planned structure
- Street
Milestone 3 of 14
Aug 22 – Oct 1, 2026Excavation
The lot has been cleared and crews are digging out about 2,673 sq ft of ground for the full cellar and foundations. Work is about two-thirds done — a final grade survey checks that the dig is level and at the right depth before foundations can start.
- Excavation progress
- 33% complete
- Up next
- Foundations · from Oct 2
- Ground being dug
- 2,673 sq ft
- Est. move-in ready
- Apr 26, 2027
Schedule
Illustrative simulation built from the project’s milestone schedule, not an official construction schedule. Dates can shift as each milestone is signed off.
Drawings & Submittals
Permit drawings by KJO Architecture
Site Photo
M-3 · ExcavationExcavation underway · October 2026
Construction cost
As listed on the building permit · Jul 2026
$575,000
- per sq ft
- ≈ $90
- per home
- ≈ $144K
- General constructionStructure, systems and finishes for all four homes$500,00087%
- ExcavationIn progress · M-3Clearing and digging out the site and cellar$75,00013%