Active milestone · M-3 Excavation

1320–22 N. Smedley Street

Three-story, four-unit apartment building

An attached, three-story building with four apartments in Cecil B. Moore, North Philadelphia, designed by KJO Architecture. This page shows the building’s progress and permit-level facts as work moves through its 14 milestones, from permits to move-in.

STORIES
3 Stories
DWELLING UNITS
4 Units
TOTAL BUILDING AREA
6,397 sq ft
ZONING
RSA-5

About the building

What’s being built at 1320–22 N. Smedley

An attached, three-story building with four apartments, designed by KJO Architecture. It fills most of the lot, with a garage at the front and a rear yard behind.

  • Full cellarA below-ground level under the building
  • BalconiesOn the second and third floors
  • Roof decksReached by a pilothouse, with a 42-inch parapet
  • Indoor parking2 spaces off Smedley St, one van-accessible
  • Fully sprinkleredFire protection to the NFPA 13 standard
  • Rooftop solarSolar collectors proposed on the roof
  • Rear yardEnclosed by a 6-ft privacy fence
  • Recessed entryA set-back ground-floor entrance
Address
1320–22 N. Smedley St, Philadelphia
Neighborhood
Cecil B. Moore, North Philadelphia
Architect
KJO Architecture
Contractor
Alex
New construction
6,397 sq ft
Zoning
RSA-5
Ground disturbed
2,673 sq ft
Permit-listed cost
$575,000

Build sequence · interactive

Watch the building go up

A step-by-step 3D simulation of how the building comes together, synced to the project’s 14 milestones. Press play or drag the timeline to see what’s happening on site and what comes next.

2 of 14 milestones complete · Est. completion Apr 26, 2027

3D model · drag to orbit

Excavation · in progress

Planned: 3 stories + roof deck

Foundations · next, from Oct 2

  • Excavation
  • Planned structure
  • Street

Milestone 3 of 14

Aug 22 – Oct 1, 2026

Excavation

In progress

The lot has been cleared and crews are digging out about 2,673 sq ft of ground for the full cellar and foundations. Work is about two-thirds done — a final grade survey checks that the dig is level and at the right depth before foundations can start.

Excavation progress
33% complete
Up next
Foundations · from Oct 2
Ground being dug
2,673 sq ft
Est. move-in ready
Apr 26, 2027

Schedule

Complete
In progress
Not started
Complete
In progress
Not started
Nov 23, 2026Day 327 of 481 · Today
Pre-Construction 1Jan 1
Pre-Construction 2May 2
ExcavationAug 22
FoundationsOct 2
FramingNov 19
RoofingDec 20
Exterior EnclosuresJan 5
Mechanical/HVACFeb 5
ElectricalFeb 16
PlumbingFeb 27
Fire SuppressionMar 10
InsulationMar 21
DrywallMar 29
Last MileApr 6
Getting ready
Below ground
Structure & shell
Systems in the walls
Finishing

Illustrative simulation built from the project’s milestone schedule, not an official construction schedule. Dates can shift as each milestone is signed off.

Drawings & Submittals

Permit drawings by KJO Architecture

Building section · KJO ArchitectureLatest revision

Site Photo

M-3 · Excavation

Excavation underway · October 2026

Construction cost

As listed on the building permit · Jul 2026

$575,000

per sq ft
≈ $90
per home
≈ $144K
  • General constructionStructure, systems and finishes for all four homes$500,00087%
  • ExcavationIn progress · M-3Clearing and digging out the site and cellar$75,00013%

Site Photos Archive

Contact the Project Team

Select a direct representative below to route your inquiry

Who are you trying to reach?

Inquiries are routed directly to accredited project team representatives.